LUKOIL OVERSEAS AND UZBEKNEFTEGAZ START THE SUPPLY OF GAS FROM KHAUZAK AREA (REPUBLIC OF UZBEKISTAN)
LUKOIL Overseas and Uzbekneftegaz, the national holding company, have
started the supply of gas from the Khauzak area (Bukhara Region of the Republic
of Uzbekistan) within the framework of implementation of the PSA for the
Kandym-Khauzak-Shady-Kungrad project.
The start of the gas supply is the most important stage of the implementation
of the Khauzak gas field development project. As of today, five wells have been
commissioned in the field, a gas treatment unit has been started, gas refining
facilities at the Mubarek gas plant and the gas transportation via the Central
Asia-Center Pipeline have been prepared.
Starting from the 8 November, continuous supply of feedstock from the wells
to the Dengizkul-Mubarek pipeline is being ensured. All equipment that has
passed the necessary inspection, start-up and commissioning and pilot operation
is working in a normal mode. The field is fully staffed; the engineering and
technical personnel underwent relevant training at the professional training
centers of the gas industry of Uzbekistan and Russia. Marketing services
started commercial operations for selling the marketable gas.
At the same time, further drilling and additional exploration of the area are
carried out using three drilling rigs. All construction, assembly and
commissioning operations are carried out at the highest technical, technological
and organizational level with obligatory observance of the strictest
environmental and industrial safety requirements. The ceremony of starting
up the Khauzak gas field will be held at the end of November this
year.
|