LUKOIL OVERSEAS COMPLETES CONSTRUCTION OF KHAUZAK GAS FIELD IN UZBEKISTAN
LUKOIL Uzbekistan, a subsidiary of LUKOIL Overseas, has commissioned the
eighth pad of gas producing wells on Khauzak in Bukhara Region, thus completing
construction of the field.
Construction of Khauzak infrastructure started back in 2006 and the main
facilities were commissioned in November 2007. The last stage of
construction work coincided with anomalously harsh winter for this region that
was the coldest one in the last 80 years (daytime temperature reached
-28 C
with stormy wind). Nevertheless, all work was completed just on time and with
high quality.
15 producing wells are currently on stream in the field, and their number
will increase to 23 by the end of the year. Necessary equipment has
already been delivered to the field base. In the third quarter this year
production of gas on Khauzak will reach its design level of more than 250
million cubic meters per month and by the end of the year 2008 the field will
reach its maximum capacity of about 300 million cubic meters of gas per month.
|